Top Price Market
  • Business
  • Politics
  • Investing
  • World
  • Business
  • Politics
  • Investing
  • World

Top Price Market

Investing

Ore Reserve Quadruples for Rhyolite Ridge Project; Reaffirms Robust Project Economics

by admin June 2, 2025
June 2, 2025

Ioneer Ltd (ASX: INR, Nasdaq: IONR) (Ioneer) is pleased to announce a 308% upgrade to the Ore Reserve estimate for its 100%-owned Rhyolite Ridge Lithium-Boron Project (‘Rhyolite Ridge’ or the ‘Project’) in Nevada, USA, alongside updated Project economics.

  • Rhyolite Ridge Ore Reserve more than quadrupled from 60 million tonnes in 2020 to 247 million tonnes, delivering a mine life of 95 years
  • Ore Reserve now contains a total of 1.92 Mt of lithium carbonate equivalent and 7.68 Mt of boric acid equivalent
  • Underpinning plans for a large, long-life, low-cost expandable operation, producing lithium carbonate, boric acid and then battery-grade lithium hydroxide
  • Stable co-product – boric acid accounts for an average 25% of annual revenue in the first 25 years; helping ensure positive EBITDA at low lithium prices and EBITDA margin of 65.7% based on average production over first 25 years
  • All-in sustaining cash cost of US$5,745 per metric tonne lithium carbonate equivalent places the Rhyolite Ridge Project in the bottom of the global lithium cost curve
  • Compelling Project economics with an after-tax NPV of US$1.367 billion, and an unlevered, after-tax internal rate of return (IRR) of 14.5%

The Ore Reserve has increased by 186.6 million tonnes (Mt) and approximately 48% of the Mineral Resource has been converted into Reserve, now estimated at:

  • 246.6 Mt at 1,464 ppm lithium and 5,444 ppm boron
  • Containing 1.92 Mt of Lithium Carbonate Equivalent (LCE) and 7.68 Mt of Boric Acid Equivalent (BAE)

“Today’s updated Reserve and Mine Plan reinforces the importance of Rhyolite Ridge’s remarkable mineralogy. Our Ore Reserve estimate of 247 Mt containing a total of 1.92 Mt LCE and 7.68 Mt BAE make it the largest lithium-boron Reserve in the world,” said Bernard Rowe, Managing Director, Ioneer. “It allows Ioneer to match prevailing market conditions and blend or prioritise ore to produce a valuable boric acid co- product, whose market is uncorrelated with the Project’s primary lithium product. No other lithium project offers this level of flexibility and economic advantage. In periods of low cycle lithium pricing, like today, we plan to prioritize the high-boron ore production to optimize the relative proportion of total revenue derived from boric acid.”

By prioritising High-Boron (Hi-B) ore in the first 25 years of production, the Project is poised to produce an average of ~19,200 tonnes per annum (tpa) of LCE, and 116,400 tpa of boric acid (see Table 1).

The updated Ore Reserve estimate, 95-year mine plan for stage one operations, and Project economics reaffirms Rhyolite Ridge as a highly attractive global Project to produce lithium carbonate, lithium hydroxide and boric acid. The updated findings position Ioneer, on an LCE basis, in the lowest cost quartile for lithium production globally with an estimated all-in sustaining cash cost to produce battery grade lithium hydroxide of US$5,745 and a cash cost of C1 $3,858 per tonne net of expected boric acid revenue in the first 25 years.

The Project has a stable overall operating cost structure to produce lithium carbonate and battery grade lithium hydroxide due to the scale and reliability of its boric acid credit. Boron remains one of the most stable natural resource commodities over many decades.

Ioneer has refined Project plans over the past four years and updates now include an Association for the Advancement of Cost Engineering (AACE) Class 2 capital cost estimate (-10%, +15%) with approximately 70% of the Project’s engineering complete. As a result of this and other engineering work including RAM analysis and detailed engineering design, Ioneer has adopted a more conservative approach to plant availability, equipment downtime and maintenance strategies. While this approach reduces bottom line economics, the Company believes it is appropriate for a Project of this type and scale.

The Company now estimates total capital expenditure to complete the Project will be US$1,667.9 million, including a 10% contingency.

Click here for the full ASX Release

This post appeared first on investingnews.com
0
FacebookTwitterGoogle +Pinterest
previous post
Blue Lagoon’s Dome Mountain Joins BC’s Select List of Permitted Projects
next post
Harmony Gold to Acquire MAC Copper in US$1.03 Billion Deal

You may also like

NorthStar Gaming Builds upon its Industry-Leading Content Vertical...

True North’s Cloncurry Copper Project Offers Strong Returns,...

FPX Nickel and JOGMEC Initiate Exploration at the...

Canadian Investment Regulatory Organization Trade Resumption – NF

Mali Court Adjourns Barrick’s Gold Complex Hearing Over...

WESTERN COPPER AND GOLD ANNOUNCES RIO TINTO EXERCISE...

Sarama Resources Updates on Progress of Cosmo Gold...

Avrupa Minerals Announces $350,000 Private Placement

Galan Secures Agreement with Glencore for Offtake &...

Blue Lagoon Completes Second Tranche of Private Placement...

    Get free access to all of the retirement secrets and income strategies from our experts! or Join The Exclusive Subscription Today And Get the Premium Articles Acess for Free


    By opting in you agree to receive emails from us and our affiliates. Your information is secure and your privacy is protected.

    Latest

    • China’s Breakthrough in Uranium Seawater Extraction Boosts Efficiency by 40 Times

    • Mali Court Adjourns Barrick’s Gold Complex Hearing Over Deepening Taxes, Control Dispute

    • Adam Rozencwajg: Gold Stock Gains, Silver and Uranium Prices — Plus PGMs Bull Case

    • GOP senators express ‘concerns,’ ‘skepticism’ over Trump’s spending bill after Musk rant

    • Mexico’s ruling party expands power in Supreme Court after elections marred by low turnout

    Categories

    • Business (1,677)
    • Investing (5,016)
    • Politics (7,899)
    • Uncategorized (2)
    • World (6,394)
    • About us
    • Contacts
    • Privacy Policy
    • Terms & Conditions
    • Email Whitelisting

    Disclaimer: toppricemarket.com, its managers, its employees, and assigns (collectively “The Company”) do not make any guarantee or warranty about what is advertised above. Information provided by this website is for research purposes only and should not be considered as personalized financial advice. The Company is not affiliated with, nor does it receive compensation from, any specific security. The Company is not registered or licensed by any governing body in any jurisdiction to give investing advice or provide investment recommendation. Any investments recommended here should be taken into consideration only after consulting with your investment advisor and after reviewing the prospectus or financial statements of the company.

    Copyright © 2025 toppricemarket.com | All Rights Reserved


    Back To Top